华人德语培训中心     Fahrschule Rainer     
显示结果从 1 到 2 共计 2 条
  1. #1
    高级会员 新生儿 alvin 的头像
    注册日期
    2008-05-10
    文章
    429
    Thanks
    1
    Thanked 1 Time in 1 Post
    声望力
    18

    预设 News of LHC incident.

    News of LHC incident.

    *************************************************************
    Source: CERN
    Content: Press Release
    Date Issued: 16 October 2008
    *************************************************************

    CERN releases analysis of LHC incident

    Geneva, 16 October 2008. Investigations at CERN* following a large helium
    leak into sector 3-4 of the Large Hadron Collider (LHC) tunnel have
    confirmed that cause of the incident was a faulty electrical connection
    between two of the accelerator’s magnets. This resulted in mechanical
    damage and release of helium from the magnet cold mass into the tunnel.

    Proper safety procedures were in force, the safety systems performed as
    expected, and no one was put at risk. Sufficient spare components are in
    hand to ensure that the LHC is able to restart in 2009, and measures to
    prevent a similar incident in the future are being put in place.

    "This incident was unforeseen," said CERN Director General Robert Aymar,
    "but I am now confident that we can make the necessary repairs, ensure
    that a similar incident can not happen in the future and move forward to
    achieving our research objectives."

    The summary report follows:

    SUMMARY OF THE ANALYSIS
    OF THE 19 SEPTEMBER 2008 INCIDENT AT THE LHC

    On 19 September 2008, during powering tests of the main dipole circuit in
    Sector 3-4 of the LHC, a fault occurred in the electrical bus connection
    in the region between a dipole and a quadrupole, resulting in mechanical
    damage and release of helium from the magnet cold mass into the tunnel.
    Proper safety procedures were in force, the safety systems performed as
    expected, and no-one was put at risk.

    After a period during which the temperature of the magnets in question was
    allowed to rise close to room temperature, inspections started and a
    number of clear findings have now been established. Investigations are
    continuing and the complete findings will be reported at a later date.

    A - In the following summary, a brief description is given of the
    chain of events which occurred around mid-day on 19th September. A more
    detailed technical report is available at
    https://edms.cern.ch/file/973073 ... dent_at_LHC__2_.pdf

    1. During the ramping-up of current in the main dipole circuit at the
    nominal rate of 10 A/s, a resistive zone developed leading in less than
    one second to a resistive voltage of 1 V at 9 kA. The power supply, unable
    to maintain the current ramp, tripped off and the energy discharge switch
    opened, inserting dump resistors into the circuit to produce a fast
    current decrease. In this sequence of events, the quench detection, power
    converter and energy discharge systems behaved as expected. Prior to this
    fast discharge, it is certain that a magnet quench can be excluded as the
    cause of the initial event. During the discharge, many magnet quenches
    were triggered automatically in the arc and the helium from their cold
    masses was recovered through the self actuated relief valves.

    2. Within one second, an electrical arc developed, puncturing the
    helium enclosure and leading to a release of helium into the insulation
    vacuum of the cryostat. After 3 and 4 seconds, the beam vacuum also
    degraded in beam pipes 2 and 1, respectively. Then the insulation vacuum
    started to degrade in the two neighbouring subsectors*.

    3. The spring-loaded relief discs on the vacuum enclosure opened when
    the pressure exceeded atmospheric, thus releasing helium into the tunnel,
    but they were unable to contain the pressure rise below the nominal 0.15
    MPa in the vacuum enclosure of the central subsector, thus resulting in
    large pressure forces acting on the vacuum barriers separating the central
    subsector from the neighbouring subsectors.

    B - After restoring power and services in the tunnel and ensuring
    mechanical stability of the magnets, the investigation teams proceeded to
    open up the cryostat sleeves in the interconnections between magnets,
    starting from the central subsector. This confirmed the lsocation of the
    electrical arc, showed absence of electrical and mechanical damage in
    neighbouring interconnections, but revealed contamination by soot-like
    dust which propagated over some distance in the beam pipes . It also
    showed damage to the multilayer insulation blankets of the cryostats.
    The forces on the vacuum barriers attached to the quadrupoles at the
    subsector ends were such that the cryostats housing these quadrupoles
    broke their anchors in the concrete floor of the tunnel and were moved
    away from their original positions, with the electric and fluid
    connections pulling the dipole cold masses in the subsector from the cold
    internal supports inside their undisplaced cryostats. The displacement of
    the quadrupoles cryostats damaged "jumper" connections to the cryogenic
    distribution line, but without rupturing its insulation vacuum.

    C - Pending further inspection of the inside of the dipole cryostats,
    it has been established that the number of magnets to be repaired is at
    most 5 quadrupoles and 24 dipoles from the three subsectors involved. But
    it is possible that more magnets will have to be removed from the tunnel
    for cleaning and exchange of multilayer insulation. Spare magnets and
    spare components appear to be available in adequate types and sufficient
    quantities to allow replacement of the damaged ones during the forthcoming
    shutdown. The extent of contamination to the beam vacuum pipes is not yet
    fully mapped, but is known to be limited; in situ cleaning is being
    considered to keep the number of magnets to be removed to a minimum. The
    plan for removal/reinstallation, transport and repair of magnets in Sector
    3-4 is being established and integrated with the maintenance and
    consolidation work to be performed during the winter shutdown across the
    whole CERN facility. The corresponding manpower resources have been
    secured.

    D - Once all possible inspections are completed, an analysis of the
    events will lead to recommendations for future actions to prevent the
    reoccurrence of this type of initial event, and to mitigate its
    consequences should it accidentally reoccur. Although the cause of the
    initial growth of connection resistance has not yet been established, and
    knowing that a similar event has not occurred in the test of all other
    sectors and of their thousands of connections, it has nonetheless been
    decided that additional measurements to generate early warnings and
    interlocks, improvements in pressure relief devices and in external
    anchoring of the quadrupole cryostats with vacuum barrier will be
    implemented before any further powering of the LHC circuits at high
    current.


    Technical appendix: LHC design
    * The arcs of the LHC, extending over most of the length of each 3.3 km
    long sector, are composed of a periodic lattice, the elementary cell of
    which (107 m long) is composed of a horizontally focusing quadrupole,
    three dipoles, a vertically focusing quadrupole and another three dipoles.
    In each family, the magnets are electrically powered in series throughout
    the sector. The magnets, equipped with their helium vessel and end covers,
    constitute the "cold masses", which, in normal operation, contain
    superfluid helium at 1.9 K and 0.13 MPa, and are thermally insulated from
    the vacuum enclosure. The neighbouring cold masses are electrically and
    hydraulically interconnected. The weight of the cold mass is transmitted
    to the vacuum enclosure via cold support posts and is further transmitted
    to the tunnel floor by adjustable support jacks, anchored in the concrete.
    The lattice cell corresponds to the extent of the local cooling loops of
    the cryogenic system, fed from the cryogenic distribution line through a
    "jumper" connection every 107 m at the location of a quadrupole. Two
    subsequent cells constitute a vacuum subsector sharing a common insulation
    vacuum; the insulation vacuum enclosures of neighbouring subsectors are
    separated by "vacuum barriers". The two beam pipes constitute two other
    separate vacuum systems, extending over the whole length of the continuous
    cryostat, and segmented at the arc ends.

  2. #2
    版主 小学二年级 此帖已删 的头像
    注册日期
    2006-12-31
    住址
    Wien
    文章
    2,532
    Thanks
    0
    Thanked 1 Time in 1 Post
    声望力
    21

    预设 回复: News of LHC incident.

    thanks for posting
    more news of this kind pls


    PI = 3.123456789....

主题讯息

目前查看此主题的会员

目前有1位用户正在查看此主题。(0 位会员和 1 游客)

发文规则

  • 不可以发表新主题
  • 不可以发表回复
  • 不可以上传附件
  • 不可以编辑自己的文章
  •